Plumbing Commissioning Checklist

Use the Plumbing Commissioning Checklist to ensure all plumbing systems are properly installed, leak-free, and functioning, including fixtures, pipes, etc.

Plumbing Commissioning Checklist



Delivery Inspection

1. Is the supplier's consolidated delivery ticket available, showing all equipment and ancillaries for inspection and used for verification?


Photo Comment

2. Is a copy of the order sent to the supplier available for reference and used for verification?


Photo Comment

3. Is the pipework packaged with end caps to protect the internal surfaces?


Photo Comment

4. Does the pipework have the correct wall thickness?


Photo Comment

5. Does the pipework have the correct flanges?


Photo Comment

6. Is the pipework dry internally?


Photo Comment

7. Is the pipework undamaged?


Photo Comment

8. Are the pipework surfaces clean and not scratched?


Photo Comment

9. Has red oxide paint been applied where required, and is it in good condition?


Photo Comment

10. Are all ancillaries included in the delivery as per the order and delivery note?


Photo Comment

11. Has any protection been removed?


Photo Comment
Storage Area

1. Is the area internal and protected from weather?


Photo Comment

2. If the pipework is stored externally, is there sufficient protection to shield it from weather and ambient conditions?


Photo Comment

3. Is the surface where the pipework is to be placed flat?


Photo Comment

4. Is the area well covered and protected?


Photo Comment

5. Is the area well-ventilated with no risk of high humidity?


Photo Comment

6. Is the area clean and dust-free?


Photo Comment
Pipework Storage

1. Will the pipework not be over-stacked?


Photo Comment

2. Will no materials be stacked on the pipework?


Photo Comment

3. Will all ancillaries be placed in a safe and secure location to prevent loss or damage?


Photo Comment

4. Are pipework/connection caps protecting the flanges not removed?


Photo Comment

5. Will the pipework be raised from the floor to allow airflow and prevent water ingress?


Photo Comment
Pre-Installation Inspection

1. Is the bracketry ready, able to bear the weight of the installation, and spaced correctly?


Photo Comment

2. Is the room/area dry and watertight?


Photo Comment

3. Is the area where the installation is being done not prone to flooding or water ponding?


Photo Comment

4. Is the room/area where the pipework will be installed clean and dust-free? If there is dust or construction work, is the pipework protected from concrete dust, cement, etc.?


Photo Comment

5. Are all connection kits, including gaskets and bolts, available to allow bolting up of the pipework?


Photo Comment

6. Is the pipework clean and free of damage?


Photo Comment
Maintenance/Access

1. Is there enough space around and above the pipework once installed to perform maintenance and remove components, where required?


Photo Comment
General

1. Is the pipework installed in line with the project drawings (size, location)?


Photo Comment

2. Is the piping free to expand and contract without noise or damage to hangers, joints, or the building?


Photo Comment

3. Are seismic restraints installed where required?


Photo Comment

4. Does the pipework avoid putting undue stress on connected equipment and is it bracketed to support itself?


Photo Comment

5. Do all piping supports and hangers meet the criteria set out in the specifications?


Photo Comment

6. Is the piping installed with sufficient pitch and arranged to ensure proper drainage and venting of the entire system?


Photo Comment

7. Are manual air vents provided at high points in closed water systems?


Photo Comment

8. Are all gaskets installed and sealed?


Photo Comment

9. Are all bolts installed as per the manufacturer’s instructions?


Photo Comment

10. Are nipples made of the same material as the pipe?


Photo Comment

11. Are connections between copper and steel pipes made with dielectric fittings?


Photo Comment

12. Is a union provided ahead of each screwed valve, trap, or strainer, and on each side of each piece of equipment, as needed to dismantle the piping?


Photo Comment

13. Are changes in pipe sizes made with proper size-reducing fittings, reducing elbows, or reducing tees? Are bushings avoided?


Photo Comment

14. Do all fittings meet specification requirements?


Photo Comment

15. Are all fittings and ancillaries rated correctly and in line with the pressure of the system?


Photo Comment

16. Is all equipment requiring maintenance accessible (e.g., valves, junction boxes)?


Photo Comment

17. Does the piping avoid blocking access to equipment that is part of this system or another system (e.g., air terminal units)?


Photo Comment

18. Are drain valves provided at all low points in hose bib piping to facilitate seasonal draining?


Photo Comment

19. Are all valves (isolation, commissioning, non-return, etc.) installed as per the drawings?


Photo Comment

20. Are all strainers installed as per the drawings and are the baskets clean?


Photo Comment

21. Is the pipework insulated as per the specification and vapor sealed where required?


Photo Comment

22. Is the piping installed to ensure that insulation will not contact adjacent surfaces?


Photo Comment

23. Are any pipe openings temporarily sealed to maintain system cleanliness?


Photo Comment

24. Are all components, including valves and controls, labeled in line with the project naming convention?


Photo Comment

25. Have instruments, flow meters, energy meters, and commissioning stations been installed in line with the manufacturer’s requirements and correct direction, including proper distances from turbulent flows?


Photo Comment

26. Are all pressure gauges installed and displaying scales as per design requirements?


Photo Comment

27. Has the pipework been magnetic weld tested, where specified?


Photo Comment

28. Has the pipework been ultrasonic weld tested, where specified?


Photo Comment

29. Has the system been filled and bled with air removed?


Photo Comment

30. Has the pipework been pressure tested?


Photo Comment

31. Has the pipework been internally flushed, cleaned, and chemically treated?


Photo Comment
Documentation

1. Have all drawings been updated to reflect any changes made?


Photo Comment

Is this sample what you are looking for?
Sign up to use & customise this template, or create your own custom checklist:

Checklist by GoAudits.com – Please note that this checklist is intended as an example. We do not guarantee compliance with the laws applicable to your territory or industry. You should seek professional advice to determine how this checklist should be adapted to your workplace or jurisdiction.

Easy inspection app for your digital checklists