Cooling Tower Commissioning Checklist

Use the Cooling Tower Commissioning Checklist to verify the installation, and operation of cooling towers, including water flow, temperature, and controls.

Cooling Tower Commissioning Checklist



109 questions in 20 sectionsInteractive preview: try the answers

Section 1 of 20 · 6 questions

Access

  1. Is the portable crane installed in line with the manufacturer’s instructions and undamaged?

  2. Is the ladder safety cage installed and undamaged for access to the roof/fan deck of the tower?

  3. Is the guard rail system installed and undamaged for access around the roof/fan deck of the tower?

  4. Is the access door platform installed and undamaged for access to the tower door if installed on a high steelwork frame?

  5. Is the maintenance platform installed and undamaged for access around the tower and are any motors/parts mounted on the tower’s external frame?

  6. Is the internal plenum walkway installed and undamaged for access inside the tower?

Section 2 of 20 · 5 questions

Ambient Air Intake & Fill Pack

  1. Is the position of the ambient air intake in line with the design and manufacturer requirements, and is it not affected by space restrictions or recirculation of surrounding exhaust ducts?

  2. Are all attenuators installed as shown on the drawings?

  3. Is the fill pack installed correctly with the correct fixings, in line with the manufacturer’s instructions?

  4. Is the fill pack clean?

  5. Can the fill pack be easily removed for cleaning and maintenance?

Section 3 of 20 · 7 questions

Balance Pipework / Equalizing Pipework

  1. Are the pipework and connections the correct size and in line with the drawing?

  2. Does the installation of the pipework avoid putting stress on the cooling tower connections or creating vibrations?

  3. Will the materials used between the cooling towers and the pipework system prevent electrolysis?

  4. Has the pipework that is to connect to the cooling tower been weld tested?

  5. Has the pipework that is connected to the cooling tower been pressure tested?

  6. Has the pipework that is connected to the cooling tower been cleaned and flushed?

  7. Are all expansion/rubber bellows installed?

Section 4 of 20 · 1 question

Bleed-Off/Blowdown Connection

  1. Is the bleed-off/blowdown water connected, the correct size, clean, and undamaged?

Section 5 of 20 · 2 questions

Controls

  1. Are all sensors and instruments installed as per the control logic/manufacturer’s wiring drawings?

  2. Are all sensors calibrated?

Section 6 of 20 · 4 questions

Controls System/Valves & Interlocks

  1. Are motorized valves installed as per the drawings, and do they open and close freely?

  2. Have all controls and panels been installed to operate the valves, fans, and interlocks?

  3. Are freezing safety interlocks installed as per the design?

  4. Are pressure differential measuring devices installed across all strainers?

Section 7 of 20 · 1 question

Drift Eliminator

  1. Are the drift eliminators installed as per the manufacturer’s requirements, the correct size, properly fixed, clean, and undamaged?

Section 8 of 20 · 2 questions

Ductwork

  1. Is the fan housing cowl/ducting installed with the relevant mesh and unobstructed?

  2. Does the mesh-free area meet the design requirements?

Section 9 of 20 · 6 questions

Electric Heater

  1. Is the electric heater installed for freeze protection, clean, and undamaged?

  2. Are the heater elements free from obstruction by debris?

  3. Has all electrical testing been completed, including torque tests of connections?

  4. Are all safety components connected and operational, including thermostats to cut power to the heater if needed?

  5. Is all control cabling connected and installed in line with the manufacturer’s/design drawings?

  6. Is power available to the electric heater/control panel for operation?

Section 10 of 20 · 10 questions

Electrical General

  1. Are the cooling tower and components fully earthed in line with the manufacturer’s instructions?

  2. Has earthing been tested?

  3. Is an emergency disconnect installed for each component in line with NFPA/local code requirements?

  4. Does the electrical voltage from the site match the cooling tower motor's required voltages?

  5. Is all cabling installed and connected on the correct containment/raceways and undamaged?

  6. Has all cabling been tested/torque tested?

  7. Has a local motor control panel (LMCP) been installed?

  8. Has the local motor control panel been electrically tested?

  9. Is all electrical cabling labeled in line with the project naming convention?

  10. Is the cooling tower ready for energization?

Section 11 of 20 · 11 questions

Fan & Motor

  1. Are the electrical connections and cables complete, fully tested, and torqued according to project/manufacturer requirements?

  2. Is motor protection installed and operating (e.g., overload protection)?

  3. Are the motor protections calibrated?

  4. Is the voltage from electrical systems correct for the cooling tower requirements (within +/-10%)?

  5. Is the fan housing clean and dust-free?

  6. Are the fan, blades, and motors clean and dust-free?

  7. Is the fan wheel centered on the intake section?

  8. Have the fixings been checked for tightness (torque)?

  9. Is the impeller balanced?

  10. Does the fan/motor rotate in the correct direction with no obstructions when turned by hand?

  11. Does the fan/motor rotate in the correct direction with no obstructions when electrically bumped on?

Section 12 of 20 · 12 questions

General

  1. Has the cooling tower information been documented from its nameplates and cross-referenced with the specified information to ensure correctness?

  2. Is the cooling tower level?

  3. Are all gaskets installed and sealed?

  4. Are all cleats and fixings installed as per the manufacturer’s instructions?

  5. Can all access doors be opened and closed with no gaps or leakage?

  6. Have all transport bolts and feet been removed?

  7. Is the fan housing ducting, if being used, installed, and fixed?

  8. Are all vibration mounts installed?

  9. Are seismic restraints, where required, installed?

  10. Are there no leaks from the tower base, and are all joints sealed?

  11. Are the cooling tower and all components, including valves and controls, labeled according to the project naming convention?

  12. Is the operation and startup manual for the cooling tower available?

Section 13 of 20 · 2 questions

Makeup Water Connection

  1. Is the makeup water connected, the correct size, and is the float/level valve correctly set?

  2. Is the float valve undamaged?

Section 14 of 20 · 1 question

Overflow Pipework

  1. Is the overflow pipework connected, the correct size, clean, and undamaged?

Section 15 of 20 · 13 questions

Pipework From Tower

  1. Are the pipework and connections the correct size and in line with the drawing?

  2. Does the installation of the pipework avoid putting stress on the cooling tower connections or creating vibrations?

  3. Will the materials used between the cooling towers and the condenser water system prevent electrolysis?

  4. Has the pipework that connects to the cooling tower been weld-tested?

  5. Has the pipework that connects to the cooling tower been pressure-tested?

  6. Has the pipework that connects to the cooling tower been cleaned and flushed?

  7. Is the pipework insulated and vapor sealed where required?

  8. Is the insulation labeled?

  9. Are all pressure gauges installed and displaying the scale as per design requirements?

  10. Are all valves/control valves installed and oriented in the correct direction?

  11. Are all commissioning devices installed in line with the manufacturer’s instructions, including the expected diameters to prevent turbulence?

  12. Are all strainers installed and inspected to ensure the mesh is clean?

  13. Are all expansion/rubber bellows installed?

Section 16 of 20 · 13 questions

Pipework To Nozzles

  1. Are the pipework and connections the correct size and in line with the drawings?

  2. Does the installation of the pipework avoid putting stress on the cooling tower connections or creating vibrations?

  3. Will the materials used between the cooling towers and the condenser water system prevent electrolysis?

  4. Has the pipework that connects to the cooling tower been weld-tested?

  5. Has the pipework that connects to the cooling tower been pressure-tested?

  6. Has the pipework that connects to the cooling tower been cleaned and flushed?

  7. Is the pipework insulated and vapor sealed where required?

  8. Is the insulation labeled?

  9. Are all pressure gauges installed and displaying scales as per design requirements?

  10. Are all valves/control valves installed and oriented in the correct direction?

  11. Are all commissioning devices installed in line with the manufacturer’s instructions, including expected diameters to avoid turbulence?

  12. Are all strainers installed and inspected to ensure the mesh is clean?

  13. Are all expansion/rubber bellows installed?

Section 17 of 20 · 7 questions

Pond/Cold Water Basin

  1. Does the access door open and close properly, and is it undamaged?

  2. Is the basin the correct size?

  3. Is the basin clean and free of debris?

  4. Is the water level correct, and is the float valve aligned with the design/manufacturer’s instructions?

Checklist by GoAudits. This checklist is an example: we do not guarantee compliance with the laws applicable to your territory or industry. Seek professional advice to adapt it to your workplace or jurisdiction.

Free PDF

Download the Cooling Tower Commissioning Checklist