Cooling Tower Commissioning Checklist

Use the Cooling Tower Commissioning Checklist to verify the installation, and operation of cooling towers, including water flow, temperature, and controls.

Cooling Tower Commissioning Checklist



General

1. Has the cooling tower information been documented from its nameplates and cross-referenced with the specified information to ensure correctness?


Photo Comment

2. Is the cooling tower level?


Photo Comment

3. Are all gaskets installed and sealed?


Photo Comment

4. Are all cleats and fixings installed as per the manufacturer’s instructions?


Photo Comment

5. Can all access doors be opened and closed with no gaps or leakage?


Photo Comment

6. Have all transport bolts and feet been removed?


Photo Comment

7. Is the fan housing ducting, if being used, installed, and fixed?


Photo Comment

8. Are all vibration mounts installed?


Photo Comment

9. Are seismic restraints, where required, installed?


Photo Comment

10. Are there no leaks from the tower base, and are all joints sealed?


Photo Comment

11. Are the cooling tower and all components, including valves and controls, labeled according to the project naming convention?


Photo Comment

12. Is the operation and startup manual for the cooling tower available?


Photo Comment
Electrical General

1. Are the cooling tower and components fully earthed in line with the manufacturer’s instructions?


Photo Comment

2. Has earthing been tested?


Photo Comment

3. Is an emergency disconnect installed for each component in line with NFPA/local code requirements?


Photo Comment

4. Does the electrical voltage from the site match the cooling tower motor's required voltages?


Photo Comment

5. Is all cabling installed and connected on the correct containment/raceways and undamaged?


Photo Comment

6. Has all cabling been tested/torque tested?


Photo Comment

7. Has a local motor control panel (LMCP) been installed?


Photo Comment

8. Has the local motor control panel been electrically tested?


Photo Comment

9. Is all electrical cabling labeled in line with the project naming convention?


Photo Comment

10. Is the cooling tower ready for energization?


Photo Comment
Variable Speed Drive

1. Has a variable speed drive (VSD) been installed?


Photo Comment

2. Has the variable speed drive (VSD) been electrically tested?


Photo Comment

3. Has the variable speed drive (VSD) been functionally tested?


Photo Comment
Controls System/Valves & Interlocks

1. Are motorized valves installed as per the drawings, and do they open and close freely?


Photo Comment

2. Have all controls and panels been installed to operate the valves, fans, and interlocks?


Photo Comment

3. Are freezing safety interlocks installed as per the design?


Photo Comment

4. Are pressure differential measuring devices installed across all strainers?


Photo Comment
Ambient Air Intake & Fill Pack

1. Is the position of the ambient air intake in line with the design and manufacturer requirements, and is it not affected by space restrictions or recirculation of surrounding exhaust ducts?


Photo Comment

2. Are all attenuators installed as shown on the drawings?


Photo Comment

3. Is the fill pack installed correctly with the correct fixings, in line with the manufacturer’s instructions?


Photo Comment

4. Is the fill pack clean?


Photo Comment

5. Can the fill pack be easily removed for cleaning and maintenance?


Photo Comment
Pond/Cold Water Basin

1. Does the access door open and close properly, and is it undamaged?


Photo Comment

2. Is the basin the correct size?


Photo Comment

3. Is the basin clean and free of debris?


Photo Comment

4. Is the water level correct, and is the float valve aligned with the design/manufacturer’s instructions?


Photo Comment

5. Is the access platform installed, clean, and undamaged?


Photo Comment

6. Is the basin guard fitted, clean, and undamaged?


Photo Comment

7. Is the vortex preventer installed, clean, and undamaged?


Photo Comment
Electric Heater

1. Is the electric heater installed for freeze protection, clean, and undamaged?


Photo Comment

2. Are the heater elements free from obstruction by debris?


Photo Comment

3. Has all electrical testing been completed, including torque tests of connections?


Photo Comment

4. Are all safety components connected and operational, including thermostats to cut power to the heater if needed?


Photo Comment

5. Is all control cabling connected and installed in line with the manufacturer’s/design drawings?


Photo Comment

6. Is power available to the electric heater/control panel for operation?


Photo Comment
Sweeper System

1. Is the cooling tower sweeper system installed in line with the manufacturer’s requirements, clean, and undamaged?


Photo Comment

2. Are the sweeper system pipework and nozzles clean and undamaged?


Photo Comment
Makeup Water Connection

1. Is the makeup water connected, the correct size, and is the float/level valve correctly set?


Photo Comment

2. Is the float valve undamaged?


Photo Comment
Bleed-Off/Blowdown Connection

1. Is the bleed-off/blowdown water connected, the correct size, clean, and undamaged?


Photo Comment
Side Stream Filtration Connection

1. Is the side stream filter connected, the correct size, clean, and undamaged?


Photo Comment
Overflow Pipework

1. Is the overflow pipework connected, the correct size, clean, and undamaged?


Photo Comment
Drift Eliminator

1. Are the drift eliminators installed as per the manufacturer’s requirements, the correct size, properly fixed, clean, and undamaged?


Photo Comment
Fan & Motor

1. Are the electrical connections and cables complete, fully tested, and torqued according to project/manufacturer requirements?


Photo Comment

2. Is motor protection installed and operating (e.g., overload protection)?


Photo Comment

3. Are the motor protections calibrated?


Photo Comment

4. Is the voltage from electrical systems correct for the cooling tower requirements (within +/-10%)?


Photo Comment

5. Is the fan housing clean and dust-free?


Photo Comment

6. Are the fan, blades, and motors clean and dust-free?


Photo Comment

7. Is the fan wheel centered on the intake section?


Photo Comment

8. Have the fixings been checked for tightness (torque)?


Photo Comment

9. Is the impeller balanced?


Photo Comment

10. Does the fan/motor rotate in the correct direction with no obstructions when turned by hand?


Photo Comment

11. Does the fan/motor rotate in the correct direction with no obstructions when electrically bumped on?


Photo Comment
Ductwork

1. Is the fan housing cowl/ducting installed with the relevant mesh and unobstructed?


Photo Comment

2. Does the mesh-free area meet the design requirements?


Photo Comment
Access

1. Is the portable crane installed in line with the manufacturer’s instructions and undamaged?


Photo Comment

2. Is the ladder safety cage installed and undamaged for access to the roof/fan deck of the tower?


Photo Comment

3. Is the guard rail system installed and undamaged for access around the roof/fan deck of the tower?


Photo Comment

4. Is the access door platform installed and undamaged for access to the tower door if installed on a high steelwork frame?


Photo Comment

5. Is the maintenance platform installed and undamaged for access around the tower and are any motors/parts mounted on the tower’s external frame?


Photo Comment

6. Is the internal plenum walkway installed and undamaged for access inside the tower?


Photo Comment
Pipework To Nozzles

1. Are the pipework and connections the correct size and in line with the drawings?


Photo Comment

2. Does the installation of the pipework avoid putting stress on the cooling tower connections or creating vibrations?


Photo Comment

3. Will the materials used between the cooling towers and the condenser water system prevent electrolysis?


Photo Comment

4. Has the pipework that connects to the cooling tower been weld-tested?


Photo Comment

5. Has the pipework that connects to the cooling tower been pressure-tested?


Photo Comment

6. Has the pipework that connects to the cooling tower been cleaned and flushed?


Photo Comment

7. Is the pipework insulated and vapor sealed where required?


Photo Comment

8. Is the insulation labeled?


Photo Comment

9. Are all pressure gauges installed and displaying scales as per design requirements?


Photo Comment

10. Are all valves/control valves installed and oriented in the correct direction?


Photo Comment

11. Are all commissioning devices installed in line with the manufacturer’s instructions, including expected diameters to avoid turbulence?


Photo Comment

12. Are all strainers installed and inspected to ensure the mesh is clean?


Photo Comment

13. Are all expansion/rubber bellows installed?


Photo Comment
Pipework From Tower

1. Are the pipework and connections the correct size and in line with the drawing?


Photo Comment

2. Does the installation of the pipework avoid putting stress on the cooling tower connections or creating vibrations?


Photo Comment

3. Will the materials used between the cooling towers and the condenser water system prevent electrolysis?


Photo Comment

4. Has the pipework that connects to the cooling tower been weld-tested?


Photo Comment

5. Has the pipework that connects to the cooling tower been pressure-tested?


Photo Comment

6. Has the pipework that connects to the cooling tower been cleaned and flushed?


Photo Comment

7. Is the pipework insulated and vapor sealed where required?


Photo Comment

8. Is the insulation labeled?


Photo Comment

9. Are all pressure gauges installed and displaying the scale as per design requirements?


Photo Comment

10. Are all valves/control valves installed and oriented in the correct direction?


Photo Comment

11. Are all commissioning devices installed in line with the manufacturer’s instructions, including the expected diameters to prevent turbulence?


Photo Comment

12. Are all strainers installed and inspected to ensure the mesh is clean?


Photo Comment

13. Are all expansion/rubber bellows installed?


Photo Comment
Balance Pipework / Equalizing Pipework

1. Are the pipework and connections the correct size and in line with the drawing?


Photo Comment

2. Does the installation of the pipework avoid putting stress on the cooling tower connections or creating vibrations?


Photo Comment

3. Will the materials used between the cooling towers and the pipework system prevent electrolysis?


Photo Comment

4. Has the pipework that is to connect to the cooling tower been weld tested?


Photo Comment

5. Has the pipework that is connected to the cooling tower been pressure tested?


Photo Comment

6. Has the pipework that is connected to the cooling tower been cleaned and flushed?


Photo Comment

7. Are all expansion/rubber bellows installed?


Photo Comment
Controls

1. Are all sensors and instruments installed as per the control logic/manufacturer’s wiring drawings?


Photo Comment

2. Are all sensors calibrated?


Photo Comment

Is this sample what you are looking for?
Sign up to use & customise this template, or create your own custom checklist:

Checklist by GoAudits.com – Please note that this checklist is intended as an example. We do not guarantee compliance with the laws applicable to your territory or industry. You should seek professional advice to determine how this checklist should be adapted to your workplace or jurisdiction.

Easy inspection app for your digital checklists