- Library
- Property Inspection
- Tile Work Inspection Checklist for Floor and Wall Tiling
Tile Work Inspection Checklist for Floor and Wall Tiling
50 questions in 9 sectionsInteractive preview: try the answers
Section 1 of 9 · 6 questionsDocumentation And Approvals
Tile type, size, and finish match the approved sample and specification
Adhesive and grout products match the specification for the substrate and area
Tile batch and shade numbers are recorded for each area
Waterproofing membrane in wet areas is inspected and signed off before tiling
Tile layout drawing showing setting-out points and joint positions is approved
Preceding trades in the area (plumbing, electrical, plastering) are signed off
Section 2 of 9 · 4 questionsMaterials On Site
Tiles are stored dry, flat, and protected from damage
Delivered tiles are checked for chips, cracks, and warping before use
Adhesive and grout bags are sealed, dry, and within their use-by date
Specified trims, spacers, and leveling clips are on site in sufficient quantity
Section 3 of 9 · 7 questionsSubstrate Preparation
Substrate is clean and free of dust, laitance, grease, and loose material
Substrate is sound, with no cracks, hollow render, or flaking areas
Concrete, screed, or render has cured for the period set in the specification
Substrate flatness is within the specified tolerance when checked with a straightedge
Primer is applied where the adhesive manufacturer requires it
Floor drains, pipe penetrations, and outlet boxes are fixed at final level
Floor screed in wet areas falls toward drains
Section 4 of 9 · 4 questionsSetting Out
Datum and level lines are marked on walls and floors
Layout avoids narrow cut tiles at edges, doorways, and openings
Wall and floor joint lines are planned to align where specified
First course of wall tiles is set level from a fixed batten or line
Section 5 of 9 · 6 questionsLaying In Progress
Adhesive is mixed to the manufacturer's ratio and used within its pot life
Notched trowel size suits the tile format and substrate
Large-format tiles are back-buttered in addition to troweled adhesive
A lifted tile shows adhesive coverage meeting the specified minimum
Spacers or a leveling system keep joint widths consistent
Movement joints are placed at perimeters, over structural joints, and at specified intervals
Section 6 of 9 · 6 questionsWall Tiling
Wall tiles are plumb and true when checked with a straightedge and level
Horizontal joints run level and vertical joints run plumb
External corners are finished with the specified trim or a clean miter
Cuts around switches, outlets, and pipes are neat and covered by plates or escutcheons
No hollow areas are found when wall tiles are tapped
Splashback and wainscot heights match the drawings
Section 7 of 9 · 7 questionsFloor Tiling
Floor surface is flat within the specified tolerance over a straightedge
Lippage between adjacent tiles is within the specified tolerance
Floor falls to drains with no ponding during a flood test
No hollow areas are found when floor tiles are tapped
Floor joints align with skirting and wall tile joints where specified
Thresholds and transitions to other floor finishes are flush or trimmed as specified
Slip resistance rating of floor tiles suits wet, external, and ramped areas
Section 8 of 9 · 5 questionsGrout, Sealant, And Movement Joints
Grout type and color match the approved specification
Grout joints are fully filled, even, and free of pinholes and cracks
Internal corners and changes of plane are sealed with flexible sealant, not grout
Sealant is continuous around baths, shower trays, basins, and pipe penetrations
Movement joints are free of grout and filled with the specified sealant
Section 9 of 9 · 5 questionsFinish And Protection
No chipped, cracked, or damaged tiles are visible from a standing position
Tile surfaces are free of grout haze, adhesive smears, and paint drips
Shade and pattern are consistent across the area, with no visible batch variation
Finished floors are protected and closed to traffic until the grout has cured
Spare tiles from the same batch are labeled and handed over to the client
Checklist by GoAudits. This checklist is an example: we do not guarantee compliance with the laws applicable to your territory or industry. Seek professional advice to adapt it to your workplace or jurisdiction.
Free PDF
Download the Tile Work Inspection Checklist for Floor and Wall Tiling
By downloading this checklist you agree to the GoAudits privacy policy and terms of service.
NEW! Try generating a custom checklist with our free AI tool:
Easy inspection app for your digital checklists
- Conduct inspections anytime, anywhere - even offline
- Capture photos as proof of compliance or areas needing attention
- Instantly generate and share detailed reports after the inspections
- Assign & track follow-up tasks, view historical trends on a centralized dashboard