Pre-Startup Safety Review(PSSR) Checklist

The Pre-Startup Safety inspection checklist can be used to thoroughly review the status of new equipment/heavy machinery, identify risks, safety procedures, lockout/tagout, training needs, maintenance and housekeeping tasks and more.

Pre-Startup Safety Review(PSSR) Checklist



Electrical

1. Is the machine wired according to code? (National Electric Code, National Fire Protection Association)


Photo Comment

2. Is the machine grounded?


Photo Comment

3. Is the power supply correctly fused and protected?


Photo Comment

4. Will additions or modifications require an Arc Flash analysis?


Photo Comment

5. Are all electrical connections secured, cords only the length necessary, conduit only used where required (no cords running through walls, under doors, etc)?


Photo Comment

6. Is there any temporary equipment S/O cord (allowed for only 90 days) if any follow up required?


Photo Comment
Personal Protective Equipment (PPE)

1. Has PPE Hazard Analysis been conducted for new jobs?


Photo Comment

2. Is required PPE available and issued to operators?


Photo Comment

3. Have operators been properly trained in the use and care of required PPE?


Photo Comment
Noise

1. Have appropriate measures been taken to safeguard workers against noise hazards?


Photo Comment

2. Has an area survey been conducted?


Photo Comment

3. If noise is above 85 dB, has noise reduction measures been considered?


Photo Comment
Evacuation/Egress

1. Have existing means of egress been obstructed or changed (at least 28")?


Photo Comment

2. Have exit routes been rerouted if necessary?


Photo Comment

3. Have employees been trained in new exit routes?


Photo Comment

4. Has the emergency evacuation drawing been updated?


Photo Comment

5. Is head room at least 7 feet high with no overhead obstructions below 6'8"?


Photo Comment

6. Have all emergency exits been designated by appropriate signage/lighting?


Photo Comment

7. Are new sprinkler systems operational and tested?


Photo Comment

8. Fire Extinguisher accessible and adequately marked?


Photo Comment
Ventilation

1. Does the new equipment generate hazardous vapours/gasses/fumes which will require additional ventilation?


Photo Comment
Ergonomics

1. Has an ergonomic audit (ergonomic job measurement system, ergonomic assessment) been conducted of the new/modified equipment?


Photo Comment

2. Have identified ergonomic hazards been corrected?


Photo Comment
Confined Spaces & Hazardous Locations

1. Has the new equipment created a hazardous location?


Photo Comment

2. Permit required for confined spaces.


Photo Comment

3. Are all hatches and other means of entry labelled as confined spaces?


Photo Comment
Fall Protection

1. The new equipment will not create a situation in which employees must work more than 4' above the floor and outside of a standard guard rail?


Photo Comment

2. Has appropriate fall protection equipment been provided to employees?


Photo Comment

3. Have employees been trained in the use of required fall protection equipment?


Photo Comment

4. No slip/trip/fall hazards created?


Photo Comment
Hazard Communication

1. The new equipment has not introduced any new hazardous chemicals into the facility.


Photo Comment

2. Have employees been trained in the hazards and protective measures for the new chemical?


Photo Comment
Training

1. Does the new/modified equipment require additional process training?


Photo Comment
Food Safety

1. Is the new equipment designed and manufactured to be easily cleaned?


Photo Comment

2. Is there a standard operating procedure in place to break down the equipment for cleaning?


Photo Comment

3. Has USDA been notified of the addition and the start-up of the equipment?


Photo Comment

4. Has the cleaning contractor been notified of the addition and the start-up date of the equipment?


Photo Comment
Air Permits

1. Has equipment received the necessary air permits?


Photo Comment

2. Has the regulatory agency been notified of start up?


Photo Comment

3. Has a standard operating procedure been modified or created to control the equipment per regulations?


Photo Comment

4. Has an updated standard operating procedure been submitted to regulators for approval?


Photo Comment

5. Does the facility have spare/redundant critical equipment to keep equipment running within compliance standards?


Photo Comment
Wastewater Compliance

1. Has the equipment received the necessary wastewater permits and/or notifications?


Photo Comment

2. Has a standard operating procedure been modified/created to control the equipment to not impact wastewater?


Photo Comment

3. Is wastewater treatment operations prepared to handle the impact of this process change?


Photo Comment
SPCC/Storm Water

1. Are secondary containment and/or storm water controls in place?


Photo Comment

2. Has the SPCC plan been updated, including site maps?


Photo Comment

3. Has a "best management practice" been created for this potential pollution source?


Photo Comment
Waste/Chemical Notification /Utilities

1. Are the procedures in place to handle the waste (hazardous or non-hazardous) from the process change?


Photo Comment

2. Has notification to regulators occurred to address legal requirements?


Photo Comment

3. Are appropriate back flow connections installed to prevent contamination of potable water?


Photo Comment

4. Are the appropriate mechanical and procedural systems installed to minimize energy/water usage?


Photo Comment
Information

1. Enter the details of Equipment/Facility


Photo Comment

2. PSSR Team Members


Photo Comment
Lockout/Tagout

1. Is the machine capable of being locked out?


Photo Comment

2. Has the equipment specific lockout/tag out procedure been developed?


Photo Comment

3. Are there any special lockout devices needed?


Photo Comment

4. Have sanitation, production, and maintenance employees been properly trained on the lockout procedures?


Photo Comment
Mechanical Hazards

1. Are equipment disconnects and operating controls labelled?


Photo Comment

2. Are the start and stop controls within easy reach of the operator?


Photo Comment

3. Is there plant maintenance for the equipment?


Photo Comment

4. Can the machine be oiled without removing the safeguards?


Photo Comment

5. Is there more than one operator?


Photo Comment

6. Are Emergency Stops working and accessible to the operator?


Photo Comment
Machine Guarding

1. Have all pinch points and points of operation been properly guarded?


Photo Comment

2. Have all chains and sprockets been properly guarded?


Photo Comment

3. Are there any exposed set screws, key ways, collars, etc?


Photo Comment

4. Have all pulleys and belts been properly guarded?


Photo Comment

5. Have augers (if present) been properly guarded?


Photo Comment

6. Are all machine guards securely attached?


Photo Comment

7. Are interlocks prohibited from being bypassed if applicable?


Photo Comment

8. Test all interlocks to ensure functioning properly if applicable?


Photo Comment

9. For saw blades, is only the length necessary to cut product exposed?


Photo Comment

10. Are all shafts ends covered with a non-rotating cap or cut down to a length of less than 1/2 the diameter of the shaft?


Photo Comment

Is this sample what you are looking for?
Sign up to use & customise this template, or create your own custom checklist:

Checklist by GoAudits.com – Please note that this checklist is intended as an example. We do not guarantee compliance with the laws applicable to your territory or industry. You should seek professional advice to determine how this checklist should be adapted to your workplace or jurisdiction.

Seeing is Believing

Get a live demo customized to your unique needs, or get started with a 14-day FREE trial.