Tank Cleaning Checklist

Use this Tank Cleaning Checklist to plan isolation, verify permits, manage hazards, confirm PPE, and document safe, compliant tank cleaning work practices.

Tank Cleaning Checklist



Isolation And Permits

1. Safety data sheets for the last stored product have been reviewed


Photo Comment

2. Chemical hazards and neutralizing agents for the residue are identified


Photo Comment

3. The tank is isolated by double block and bleed or physical blinding


Photo Comment

4. Every blind installed is recorded on a blind register


Photo Comment

5. Lockout and tagout is applied to all connected equipment and agitators


Photo Comment

6. A confined space entry permit has been issued for the work


Photo Comment

7. A hot work permit is in place where spark-producing work is planned


Photo Comment

8. The tank is electrically grounded and bonded against static discharge


Photo Comment
Atmospheric Monitoring And Gas Testing

1. Gas detection equipment has been bump tested or calibrated before use


Photo Comment

2. Oxygen concentration is within the safe range before entry


Photo Comment

3. The atmosphere is below the lower explosive limit before entry


Photo Comment

4. Toxic gas concentrations are below exposure limits before entry


Photo Comment

5. Readings are taken at top, middle and bottom levels of the tank


Photo Comment

6. Monitoring continues throughout the work rather than before entry only


Photo Comment

7. Forced ventilation is running and discharging to a safe location


Photo Comment
Confined Space Entry And Rescue

1. A trained attendant is stationed at the entry point at all times


Photo Comment

2. The attendant maintains continuous communication with entrants


Photo Comment

3. An entry log records who is inside the tank and when


Photo Comment

4. Non-entry retrieval equipment is rigged and attached to each entrant


Photo Comment

5. Rescue arrangements are confirmed available before entry begins


Photo Comment

6. Respiratory protection suited to the atmosphere is worn and fit tested


Photo Comment

7. Explosion-proof lighting and non-sparking tools are in use inside the tank


Photo Comment

8. Tools taken into the tank are counted in and counted out


Photo Comment
Product Removal And Sludge Management

1. The heel has been pumped down to the lowest level achievable


Photo Comment

2. Sludge is removed by mechanical scraper or vacuum unit


Photo Comment

3. Pyrophoric deposits are kept wet until removed from the tank


Photo Comment

4. Waste is contained in approved containers and manifested for disposal


Photo Comment

5. Chemical wash agents are compatible with the tank lining and previous product


Photo Comment

6. Wash water is captured rather than released to surface drainage


Photo Comment

7. Wash water is routed to a permitted treatment facility


Photo Comment
Internal Surface And Component Cleaning

1. Baffles, heating coils and agitator blades are cleaned of residue


Photo Comment

2. The sump and low point drains are clear of solid deposits


Photo Comment

3. The roof underside and support columns are cleaned of vapor-phase deposits


Photo Comment

4. Internal liners and coatings are inspected for blistering, peeling and thinning


Photo Comment

5. Floating roof seals and legs are cleaned and inspected where fitted


Photo Comment

6. Nozzles, manways and internal pipework are clear


Photo Comment
Mechanical Inspection And Testing

1. Non-destructive testing of the floor and shell has been carried out


Photo Comment

2. Pitting and corrosion found is recorded with its location and depth


Photo Comment

3. Internal welds are visually inspected for cracks and stress failures


Photo Comment

4. The pressure vacuum vent and thief hatch are cleaned and tested for seal and spring tension


Photo Comment

5. Secondary containment is free from cracks, standing water and debris


Photo Comment

6. Cathodic protection is inspected where fitted


Photo Comment
Recommissioning

1. The tank is dried by forced air where the next product requires it


Photo Comment

2. A gas-free certificate is issued by a qualified competent person


Photo Comment

3. The tank is confirmed product-clean against the specification for its next service


Photo Comment

4. Every blind on the register has been removed and signed off


Photo Comment

5. Gaskets and seals are replaced with new items compatible with the next product


Photo Comment

6. All tools, equipment and materials have been removed from the tank


Photo Comment

7. Lockout and tagout devices are removed and the system returned to service


Photo Comment

8. The entry permit is formally closed and signed


Photo Comment

Checklist by GoAudits.com – Please note that this checklist is intended as an example. We do not guarantee compliance with the laws applicable to your territory or industry. You should seek professional advice to determine how this checklist should be adapted to your workplace or jurisdiction.

Is this sample what you are looking for?
Sign up to use & customize this template, or create your own custom checklist.

NEW! Try generating a custom checklist with our free AI tool:

Easy inspection app for your digital checklists