Solar Commissioning Checklist
141 questions in 17 sectionsInteractive preview: try the answers
Section 1 of 17 · 10 questionsPV Modules And Module Wiring
Have MC connections been inspected for workmanship?
Are module cables properly secured to the module frame with no dangling wires?
Is the bend radius no greater than four times the diameter of the wire?
Is there no debris on the module surface, such as foam pads or sealant residue?
Is there no physical damage to module frames or laminates?
Does module wiring enter a strain relief prior to landing on any terminal block?
Is the ground wire and lug securely attached to the rails and to module frames?
For the Array GEC connection, is the wire size, wire support, and wire type compliant with the 2008 code?
Is the string layout marked up on the array layout and recorded?
Have the serial numbers been recorded?
Section 2 of 17 · 5 questionsMounting Hardware
Is all hardware installed as designed and torqued as needed?
Is the correct hardware stack-up confirmed, such as lock washers where needed?
Are roof penetrations secured and flashed?
Is the racking properly secured to rafters or standing seams?
Does the ballasting plan conform to the manufacturer’s compliance letter?
Section 3 of 17 · 4 questionsBuilding Envelope Penetrations
Are all penetrations weather-sealed or fire-stopped around the outside of conduits?
Are all conduit raceways filled with duct seals at the first building penetration?
Are signal wiring penetrations (DAS) sealed around the outside of conduits?
Is "DC Voltage Warning" labeled on DC conduits?
Section 4 of 17 · 12 questionsDC Source Circuit Junction Box
Is the box securely fastened and sealed against the weather, with weep holes if needed?
Is the array wiring leading to the box neat and supported?
Is field wiring routed neatly within the box?
Are field wiring terminations tight?
Is field wiring properly polarity marked with colored tape or wire insulation color?
Is wire identified with permanent markers/labels (e.g., string numbers)?
Is the ground wire securely attached?
Are conduit connections tight and are bushings used if applicable?
Is a drip loop incorporated into the wiring as it enters the box?
Are locations marked on the roof layout or conduit drawing?
Are conductors rated for the location (e.g., THWN-2)?
Is there a "Warning: DC Voltages" label?
Section 5 of 17 · 13 questionsSource Circuit Fused Combiner Box
Is the box securely fastened and sealed against the weather?
Is field wiring routed neatly within the box?
Are field wiring terminations tight?
Is field wiring properly marked with colored tape or jacket color for polarity?
Is wire identified with permanent labels (e.g., String# one side)?
Is the ground wire securely attached?
Does the fuse combiner type and rating conform to the one-line diagram?
Are conduit connections tight and are bushings used if applicable (e.g., Myers)?
Is a drip loop incorporated into the wiring as it enters the box?
Is the box cover secure and tight?
Are locations marked on the roof layout or conduit drawing?
Is the combiner labeled to show which inverter or switch it goes to, and does it conform to the three-line diagram?
Is there a warning label indicating not to remove fuses under load and noting the presence of DC voltages?
Section 6 of 17 · 11 questionsDC Disconnect Switch
Is field wiring neatly routed inside the box?
Are field wiring terminations tight?
Is wire identified with permanent markers/labels?
Are fuses installed (when used)?
Do fuse types and ratings conform to the one-line diagram (when used)?
Is the ground wire securely attached?
Are conduit connections tight and are bushings used if applicable?
Is the box cover secure and tight?
Does the rating conform to the one-line diagram?
Are labels in place and do they conform to the values?
Is a locking seal installed if readily accessible?
Section 7 of 17 · 13 questionsAC Combiner Panel
Is field wiring neatly routed inside the box?
Are field wiring terminations tight?
Is field wiring properly polarity marked with colored tape or jacket color?
Is wire identified with permanent markers/labels?
Is the ground wire securely attached?
Do fuse types and ratings conform to the one-line diagram (when used)?
Are fuses installed (when used)?
Are conduit connections tight and are bushings used if applicable?
Are labels in place and do they conform to the values?
Does the combiner rating conform to the one-line diagram?
Is the box properly accessible and lockable?
Is the box cover secure and tight?
Is a locking seal installed if readily accessible?
Section 8 of 17 · 13 questionsAC Disconnect Switch
Is field wiring neatly routed inside the box?
Are field wiring terminations tight?
Is field wiring properly polarity marked with colored tape or jacket color?
Is wire identified with permanent markers/labels?
Is the ground wire securely attached?
Do fuse types and ratings conform to the one-line diagram (when used)?
Are fuses installed (when used)?
Are conduit connections tight and are bushings used if applicable?
Are labels in place and do they conform to the values?
Does the disconnect rating conform to the one-line diagram?
Is the box properly accessible and lockable?
Is the box cover secure and tight?
Is a locking seal installed?
Section 9 of 17 · 8 questionsKWh Meter
Are all wire connections tight?
Is field wiring properly polarity marked with colored tape or jacket color?
Is the ground wire securely attached (equipment ground)?
Are conduit connections tight and are bushings used if applicable?
Is the meter labeled as a solar array meter?
Is the box cover secure and tight?
Is the neutral not bonded to ground in customer-owned equipment?
Is the kWh reading recorded on the second register if applicable?
Section 10 of 17 · 2 questionsService Panel
Are labels in place?
Is there a label to identify the breaker and to indicate not to relocate?
Section 11 of 17 · 11 questionsInverter 1
Are working and ventilation clearances as per the manufacturer's specifications?
Is polarity correct for inverter connections?
Has the grounding electrode conductor been confirmed to land on the inverter where the manufacturer requires it?
Is the grounding electrode conductor not choked?
Is the grounding electrode conductor used only with irreversible connections?
Is the inverter's time and date set correctly?
Have the model number and serial number of the inverter been recorded?
Does the inverter location number match that of the three-line diagram?
Is there a warning label about "if a ground fault is indicated…"?
Checklist by GoAudits. This checklist is an example: we do not guarantee compliance with the laws applicable to your territory or industry. Seek professional advice to adapt it to your workplace or jurisdiction.
Free PDF
Download the Solar Commissioning Checklist
By downloading this checklist you agree to the GoAudits privacy policy and terms of service.
NEW! Try generating a custom checklist with our free AI tool:
Easy inspection app for your digital checklists
- Conduct inspections anytime, anywhere - even offline
- Capture photos as proof of compliance or areas needing attention