Hydrostatic Test Report Template

Use the Hydrostatic Test Report Template to record test pressure, duration, and results of hydrostatic vessels or pipes, ensuring safety standards are met.

Hydrostatic Test Report Template



57 questions in 8 sectionsInteractive preview: try the answers

Section 1 of 8 · 5 questions

Test Identification

  1. The system, line or equipment number under test is recorded

  2. The approved test procedure or test pack reference is recorded

  3. The test boundary is defined by drawing and isolation point

  4. The test supervisor, witness and contractor are named

  5. The report reference number is recorded against the test pack

Section 2 of 8 · 9 questions

Pre-Test Preparations

  1. Welds within the test boundary are complete and released for testing

  2. Joints and fittings have been visually examined with defects cleared

  3. Test blinds are installed at every boundary and listed on a blind register

  4. End caps and closures are rated for the test pressure

  5. Valves within the boundary are set to the positions required by the procedure

  6. Equipment unable to withstand test pressure has been isolated or removed

  7. Instruments, relief valves and expansion joints are removed or blanked

  8. Temporary supports are rated for the weight of the system filled with water

  9. Spring hangers and supports are pinned where the procedure requires it

Section 3 of 8 · 7 questions

Test Medium And Instrumentation

  1. The test medium matches the procedure and is clean and free of debris

  2. Chloride content of the test water is within limits for stainless steel systems

  3. The metal temperature is above the minimum required to avoid brittle fracture

  4. Gauge calibration certificates are current for every gauge in use

  5. Gauge range is selected so the test pressure falls in the middle of the scale

  6. A second gauge or chart recorder is fitted where the procedure requires it

  7. The pressure relief device is set below the lowest rated component in the boundary

Section 4 of 8 · 6 questions

Test Parameters

  1. The specified test pressure from the approved procedure is recorded

  2. The actual test pressure achieved is recorded

  3. The required hold time and the observed hold time are both recorded

  4. Ambient and fluid temperatures at the start and end of the test are recorded

  5. Start and end pressure readings are recorded with the times taken

  6. Readings were taken at the intervals specified in the procedure

Section 5 of 8 · 8 questions

Test Procedure And Safety Controls

  1. The system was vented at all high points until free of air during filling

  2. The system was filled slowly at the rate stated in the procedure

  3. Pressure was raised in stages with a hold at each stage

  4. An exclusion zone was established and maintained throughout the test

  5. Personnel remained clear of blind flanges, closures and threaded connections

  6. Nobody approached the system while it was held at full test pressure

  7. The system was not left pressurised unattended

  8. Joints and welds were examined only after pressure was reduced to inspection level

Section 6 of 8 · 7 questions

Results And Observations

  1. Pressure was maintained for the full duration without a drop beyond tolerance

  2. The system remained free of visible leakage at all joints and connections

  3. No permanent deformation or distress was observed in any component

  4. Any leaks or defects found are recorded with their location

  5. Corrective work and any retest are recorded against the original test

  6. Observations are supported by photographs or gauge chart records

  7. The test meets the acceptance criteria stated in the approved procedure

Section 7 of 8 · 8 questions

Depressurisation And Reinstatement

  1. Pressure was released in a controlled sequence at the rate stated in the procedure

  2. Vents were opened before draining to prevent vacuum forming in the system

  3. The system was drained completely with no water left in low points

  4. The system was dried where the service requires it

  5. Test water was disposed of in line with environmental requirements

  6. Every blind listed on the register has been removed and signed off

  7. Relief valves, instruments and removed components have been reinstated

  8. Valves and supports have been returned to their operating positions

Section 8 of 8 · 7 questions

Certification And Sign-Off

  1. The responsible engineer has certified the test result

  2. The test was witnessed by the client or third-party inspector where required

  3. Contractor and client representatives have signed the report

  4. The approval carries signatures, dates and stamps as required

  5. Gauge calibration certificates are attached to the report

  6. Photographs and gauge charts are attached to the report

  7. The completed report is filed against the system and the test pack

Checklist by GoAudits. This checklist is an example: we do not guarantee compliance with the laws applicable to your territory or industry. Seek professional advice to adapt it to your workplace or jurisdiction.

Free PDF

Download the Hydrostatic Test Report Template

By downloading this checklist you agree to the GoAudits privacy policy and terms of service.

NEW! Try generating a custom checklist with our free AI tool:

Easy inspection app for your digital checklists